Smart Meter Rollout Calculator

How long a smart-meter or sensor rollout takes and what it costs — from meters to fit, installs per crew per day, crews available and the share of visits that fail first time.

A rollout is installs divided by daily capacity, stretched by the visits that fail — nobody home, access refused, a meter board that needs an electrician first.

%
Results update as you type
Results
Working days to complete
393.5
Calendar months (21 working days each)
Total visits including retries
Failed visits
Meters completed per day
Total programme cost
Cost per meter installed
Crews needed to finish in 12 months
Reviewed September 2026. Planning arithmetic is universal; the rates are local and yours to set. ABS publishes population and density by SA2; state planning schemes set zoning and yield rules.
No account required · Google Analytics off unless allowedCalculator arithmetic runs in your browserResults update as you type
All calculations run 100% in your browser. The calculator code does not submit your figures to GlobalCalc to obtain a result.
About smart meter rollout

How the smart meter rollout calculator works

A rollout is installs divided by daily capacity, stretched by the visits that fail — nobody home, access refused, a meter board that needs an electrician first. A 15% failure rate adds 18% to the programme, not 15%, because failed visits are re-attempted.

The cost per meter is dominated by labour and the failed visits, which is why utilities book appointments rather than cold-call.

Formula: working days = meters × (1 + fail rate / (1 − fail rate)) / (crews × installs per crew per day)

Worked examples

InputsWorking days to completeNote
85,000 meters, 24 crews393.5about 19 months
Appointments cut failures393.5fewer wasted visits
Twice the crews196.8half the time

Frequently asked questions

How many meters can a crew fit in a day?

Eight to twelve for straightforward residential swaps, fewer where boards need upgrading first.

Why does a 15% failure rate cost more than 15%?

Because failed visits are retried, and some of those fail too. The total is 1/(1−f), so 15% failures mean 18% more visits.

What causes failed visits?

Nobody home, access refused, a meter board that is unsafe, and asbestos panels that need a specialist. Booked appointments halve the rate.

What does a rollout cost per meter?

Roughly hardware plus two to three visit-equivalents of labour. Failed visits and re-attempts are where programmes go over budget.

Does this apply to other sensors?

Yes — any programme that is one site visit per unit: water meters, streetlight controllers, air quality sensors.

Where these figures come from

Last checked: September 2026. Default per-capita rates are mid-range figures from national statistical agencies and utility reports; every one is an input you should replace with the local figure.